In the Railway Jurisdiction, Culvert & Nala desilting work not satisfied which expose by Wednesday Rain. Last 5 years Bmc paid Rs 9.60 cr for the work but Railway only spend Rs 6.59 cr and 31% till remain with Railway Treasury. Interesting Railway claims that quantity of Malba is not calculated. Its revels in a query filed by RTI Activists Anil Galgali.
Athak Seva Sangh Chairman and RTI Activists Anil Galgali ask a query regarding Culvert & Nala desilting work done by Railway and how much fund provided by Bmc in last 5 years. Central Railway Public Information Officer R K Yadav provided a information from 2009-10 to 2013-14. Mr Yadav informed Galgali that from CSTM to Kanjurmarg 30, Kanjurmarg to Mulund TNN 13 and CSTM to Mankhurd 28, total 71 culverts are there and all were desilting but they have no records because quantity of Malba is not calculated by railway. This work done by 'Culvert Per Month Basis ' Unit. Bmc paid fund Rs 7,47,34,516 but Railway only spend Rs 4,77,20,456. Rs 2,70,14,060 till balance with Railway.
Western Railway Public Information Officer and Divisional Engineer(South) informed Galgali that in there jurisdiction 43 culvert and Nallas. Last 5 year, Bmc funded Rs 2,12,08,000 in that Rs 30,79,368 till balance with western railway and for desilting Rs 1,81,28,632 spend by Railway. WR also not give actual quantity desilting done by there contractors.
A letter written to Railway Minister and Both General Manager of Central and Western Railway, Anil Galgali ask that Bmc every year without cry, funding Rs1.92 cr to Railway in there jurisdiction Culvert & Nala desilting then why railway derails in rain? Anil Galgali also demand to Railway to online all data including Quantity of Malaba and amount on there official Website and return balance amount to bmc.
Athak Seva Sangh Chairman and RTI Activists Anil Galgali ask a query regarding Culvert & Nala desilting work done by Railway and how much fund provided by Bmc in last 5 years. Central Railway Public Information Officer R K Yadav provided a information from 2009-10 to 2013-14. Mr Yadav informed Galgali that from CSTM to Kanjurmarg 30, Kanjurmarg to Mulund TNN 13 and CSTM to Mankhurd 28, total 71 culverts are there and all were desilting but they have no records because quantity of Malba is not calculated by railway. This work done by 'Culvert Per Month Basis ' Unit. Bmc paid fund Rs 7,47,34,516 but Railway only spend Rs 4,77,20,456. Rs 2,70,14,060 till balance with Railway.
Western Railway Public Information Officer and Divisional Engineer(South) informed Galgali that in there jurisdiction 43 culvert and Nallas. Last 5 year, Bmc funded Rs 2,12,08,000 in that Rs 30,79,368 till balance with western railway and for desilting Rs 1,81,28,632 spend by Railway. WR also not give actual quantity desilting done by there contractors.
A letter written to Railway Minister and Both General Manager of Central and Western Railway, Anil Galgali ask that Bmc every year without cry, funding Rs1.92 cr to Railway in there jurisdiction Culvert & Nala desilting then why railway derails in rain? Anil Galgali also demand to Railway to online all data including Quantity of Malaba and amount on there official Website and return balance amount to bmc.